U.S. Offshore Wind: An Update on Near-Term Projects
U.S. Offshore Wind: An Update on Near-Term Projects

March 24, 2025

The U.S. offshore wind industry, while making leaps and bounds in some areas, has faced a significant amount of turbulence in recent years. A recent report released by the American Clean Power Association (ACP) projects about 14 GW of wind capacity offshore U.S. coastlines by 2030, significantly shy of the goal of 30 GW set by the Biden administration in 2021. 


The 2024 Offshore Wind Market Report by National Renewable Energy Laboratory projects $65 billion will be invested in offshore wind projects by 2030. According to the report, there is 56 GW under development across 37 leases in the United States. There are currently 12 GW of projects with active offtake agreements, including 5 GW under active construction at Vineyard Wind, Revolution Wind, Sunrise Wind, and Coastal Virginia Offshore Wind. There is merely 172 MW of offshore wind capacity currently installed in the United States as of 2024. This is only a fraction of China’s current capacity (the global leader in offshore wind capacity) with nearly 38 GW online. 


Increasing material costs, high interest rates, and supply chain disruptions have led multiple offshore wind companies in the last few years to cancel or renegotiate power contracts for planned offshore wind farms. The current administration's policy shifts have also significantly reshaped the near-term trajectory of the U.S. offshore wind pipeline. Following a presidential memorandum that paused offshore wind leasing and mandated a review of existing permits, numerous projects have encountered delays, divestments, and financial write-downs due to heightened economic uncertainties. This article provides a comprehensive overview of the near-term U.S. offshore wind projects, categorizing them based on their status: operational, under construction, approved but not yet under construction, paused or delayed, and temporarily canceled.


The Overall Outlook: 

- 0.172 GW in operation 

- 5 GW under construction 

- 3.8 GW approved, not yet under construction

- 11.5 GW delayed or paused 

- 9.6 GW temporarily cancelled 


 

Projects in Operation: The U.S. currently has 172 MW (0.172 GW) of operational offshore wind capacity across three pioneering projects.


South Fork Wind: America’s first commercial scale offshore wind farm by Ørsted & Skyborn Renewables located 35 miles east of Montauk Point, NY. It’s composed of twelve Siemens Gamesa 11 MW turbines with a nameplate capacity of 130 MW. First approved by the Long Island Power Authority in 2017, construction of South Fork Wind started in January 2022 and ended in March 2024. The project powers around 70,000 Long Island homes. 


Block Island Pilot Project: A 30 MW pilot project by Ørsted off the coast of Rhode Island that is composed of five GE Haliade 6 MW offshore wind turbines which have replaced 5 diesel generators that previously powered the island. A mere 10% of the output covers 100% of Block Island’s power consumption with the rest being exported to the mainland. 


Coastal Virginia Pilot Project: A pilot project (12 MW) composed of two 6-megawatt offshore wind turbine generators located approximately 27 miles east of the city of Virginia Beach, Virginia in water depths up to 79 ft. The turbines are the first to be installed in United States federal waters and will be used to advise a larger commercial scale development. The pilot project has been fully operational since Fall 2020. 


 

Projects Under Construction: There are currently four projects under construction representing around 5 GW of renewable electricity. 


Vineyard Wind 1: Vineyard Wind is currently building the nation's first utility-scale offshore wind project over 15 miles off the coast of Massachusetts with Avangrid & Copenhagen Infrastructure Partners (CIP). The project will generate renewable energy for over 400,000 homes and businesses. The 806 MW project will consist of 62 General Electric Haliade-X turbines, each capable of generating 13 MW of electricity. 


Status: Construction activities began in Barnstable in November of 2021 where the onshore substation and onshore export cables are located. Offshore construction activities began in 2022 with offshore export cable installation. Wind turbine installation activities in the lease area began in 2023 and are ongoing. Vineyard Wind 1 achieved first power on January 2, 2024, when one turbine delivered approximately 5 MW of power to the electricity grid. On June 26, 2024, Avangrid announced that it had placed 10 turbines into production. The remaining monopile foundations and transition pieces are still being installed and cable laying operations for the inter-array cables will be conducted throughout April 2025. 


Recent News: A blade failure on July 13, 2024, resulted in a pause to construction along with immediate remediation efforts to clean up the debris. Vineyard plans to replace all blades from the GE factory in Gaspe, Canada and continue construction. As of January 17th, 2025, the Bureau of Safety and Environmental Enforcement (BSEE) has completed a review and approved the revised COP submitted by Vineyard Wind 1 and removed the suspension order on power generation and the installation of the remaining wind turbines. More information regarding the blade incident here.


Revolution Wind: Revolution Wind, the first multi-state offshore wind project will supply 715 MW of offshore wind energy to Rhode Island and Connecticut – enough clean electricity to power more than 350,000 homes. The project by Ørsted & Skyborn will consist of 65 Siemens Gamesa 11-megawatt turbines 15 miles off the Rhode Island Coast and 32 miles southeast of the Connecticut coast. Revolution Wind is adjacent to the already completed South Fork Wind project. 


Status: Local construction work on Revolution Wind began in 2023 and the project is expected to be fully operational by 2026. Ørsted installed the project’s first monopile foundation in May and its first wind turbine in September. So far they have successfully installed 52 foundations and 9 turbines at Revolution Wind. Revolution Wind Fact Sheet


Coastal Virginia Offshore Wind Project (CVOW): The largest commercial-scale offshore wind farm in the U.S. (2.6 GW) composed of 176 14.7-megawatt Siemens Gamesa turbines, which will create enough renewable energy to power up to 660,000 homes. It will be the largest offshore wind project in the nation and the first owned by an electric utility company — Dominion Energy. The CVOW project is credited with creating 2,000 direct and indirect American jobs and $2 billion of economic activity. 


Status: The project recently reached 50% completion as the final monopiles and transition pieces were installed and remains on track for completion by the end of 2026. As of November 2024, Dominion Energy announced that 78 monopile foundations and 4 offshore substation foundations were installed for the project during the first installation season. CVOW continues to achieve significant construction milestones including the successful installation of the first 16 transition pieces which serve as the junction between the foundation and tower for each of the 176 wind turbines. Delivery of the first three 4,300-ton offshore substations to the Portsmouth Marine Terminal in Virginia Beach occurred at the end of January and the first was installed by DEME Group in mid-March. Fully fabricated monopiles, transition pieces, undersea cable and other major components continue to be delivered in preparation for on-schedule installation. Wind turbine tower and blade fabrication is also underway, with nacelle fabrication to begin later this quarter. Check out the full construction timeline here.


Sunrise Wind: A 924 MW project by Ørsted consisting of 84 Siemens Gamesa 8.0-167 Direct Drive (DD) wind turbines. Located 30 miles east of Long Island’s Montauk Point, the project has the capacity to power nearly 600,000 New York homes. Click here for the latest construction updates.


Status: Onshore construction began in summer of 2024. The first phase of construction included the onshore converter station on Union Avenue in Holbrook and establishing laydown yards for equipment and material storage and set-up. As of September 2024, more than half of the advanced foundation components had already been built by Riggs Distler, as the project gears up for offshore construction in 2025. Sunrise Wind is expected to be operational sometime in 2027. Check out the latest construction report here.


 

Projects With Approval, Not Yet Under Construction: Four projects representing about 3.8 GW of renewable energy. 


Empire Wind: Empire Wind is being built by Equinor and will be located 15-30 miles southeast of Long Island. The project is being developed in two phases. Empire Wind 1 will be composed of 54 Vestas 15 MW turbines with a nameplate capacity of 810 MW, powering 500,000 New York homes. A second part of the lease area, Empire Wind 2 is currently in early-stage development with options currently being assessed. It will bring power onshore at the Sunset Park Onshore Substation, located next to the South Brooklyn Marine Terminal. After that, the power will continue to Gowanus Brooklyn Substation where it will interconnect into the New York City grid. 


Status: Equinor finalized the federal lease for Empire Wind in March 2017 and BOEM issued final approval for the Final Construction and Operations Plan (COP) in February 2024. Construction on the South Brooklyn Marine Terminal began in June 2024, with a groundbreaking ceremony. The terminal will take about two years to complete construction. Offshore construction is expected to begin in 2025, and first power is expected to be delivered in late 2026. Empire Wind 1 is expected to be fully operational by the end of 2027. Financial close was reached at the end of December 2024 with the project securing a financing package of over $3 billion USD. 


Maryland Offshore Wind Project: The Maryland Offshore Wind Project by US Wind, Inc consists of three planned phases, which include the proposed installation of up to 114 wind turbine generators, up to four offshore substation platforms, one meteorological tower, and up to four offshore export cable corridors. Two phases, known as MarWin and Momentum Wind, already have offshore renewable energy certificates from the State of Maryland. As for the third phase, the developers plan to build out the remainder of the lease area to fulfill ongoing, government-sponsored demands for offshore wind energy. US Wind, Maryland’s leader in offshore wind development, holds the lease rights to a federal lease area off the coast of Ocean City, Maryland. The lease area, about 80,000 acres in size, has the capacity to generate about 2.2 GW of offshore wind energy, which is enough electricity to power over 700,000 homes each year. 

-The first phase of US Wind’s lease area, called “MarWin,” is an offshore wind project that will deliver approximately 300 MW of clean, renewable electricity to Maryland by constructing 22 turbines or less over 20 miles from shore. This will power more than 92,000 homes each year. In addition to building MarWin, which was approved by the state in 2017, US Wind now also plans to develop Momentum Wind, a new 808 MW offshore wind project that will be located 15 miles off the coast of Maryland with up to 55 turbines. When taken together, the two projects will deliver 1,100 MW of clean energy to the grid, powering more than 340,000 homes with renewable energy. More information here: Fact Sheet


Status: On December 3rd, 2024, Bureau of Ocean Energy Management (BOEM) issued its final approval of the company’s Construction and Operations Plan (“COP”), marking the agency’s final permit on US Wind’s federal permitting application. Additionally, the National Marine Fisheries Services (“NMFS”) issued a Letter of Authorization to US Wind on November 26, 2024, marking that agency’s final authorization for US Wind’s construction in the federal lease area off the coast of Ocean City, Maryland. On December 10th, US Wind announced that the Delaware Department of Natural Resources and Environmental Control (DNREC) has approved three permit applications to connect its offshore wind power to the regional electrical grid in Sussex County, Delaware. These approvals allow US Wind to responsibly land its power cables underneath 3R’s Beach parking lot in the Delaware Seashore State Park and safely route them under the Indian River Bay, ultimately connecting to the regional electrical grid at Delmarva Power and Light’s Indian River substation in Dagsboro, Delaware. US Wind plans to begin onshore construction in 2026 and offshore construction in 2028. 


New England Wind (NEW) 1 & 2Iberdrola through Avangrid, its subsidiary in the United States is building New England 1 & 2 which will border the already operational Vineyard Wind 1 to the south in New England. Together, these three projects would have a total capacity of up to 2.6 GW of clean, renewable energy that BOEM estimates could power more than 900,000 homes each year. The projects are situated approximately 20 nautical miles (nm) south of Martha’s Vineyard, Massachusetts, and about 24 nm southwest of Nantucket, Massachusetts. The Construction and Operations plan (COP) includes up to 129 wind turbine generators, with up to five offshore export cables transmitting electricity to onshore transmission systems in the Town of Barnstable and Bristol County, Massachusetts. In July 2024, Avangrid announced that it had received full federal approval of the COP for the New England Wind 1 and 2 offshore projects. The approval of the COP follows the favorable Record of Decision (ROD) issued by the Biden Administration in April 2024. 


Status: On May 15, 2024, the New England Wind project was segregated into two leases, New England Wind 1 (OCS-A 0534) and New England Wind 2 (OCS-A 0561). The northern portion of the original lease was retained by Park City Wind, LLC for the New England Wind 1 Project, formerly Phase 1, and retains the original lease number given by BOEM. The southern portion of the original lease was assigned to Commonwealth Wind, LLC and is now referred to as the New England Wind 2 project, formerly Phase 2. Avangrid had already secured power purchase agreements (PPAs) for the two projects with the state electric distribution companies in Massachusetts (for Commonwealth Wind) and Connecticut (for Park City Wind). However, the developer terminated both PPAs in 2023 with plans to re-enter the projects into new state solicitations. Last march, Avangrid submitted a combined proposal for the two projects which offer the region 1,870 MW of offshore wind power, enough to power nearly 1 million homes. The developer noted that New England Wind 2 is only offered as a combined project with New England Wind 1 to capture important economics of scale and support significant grid upgrades. They also submitted a proposal for just the NEW 1 project, slated to deliver 791 MW


NEW 1 (retained by Park City Wind): The first phase of the project will have an installed capacity of 791 MW, enough energy to power 400,000 homes in the region. With local, state, and federal permits, all interconnection rights secured, and a Project Labor Agreement signed, Avangrid is awaiting approval of a power purchase agreement to begin building this new project in 2025, which is slated to reach full commercial operation by 2029. As of September 6th 2024: Massachusetts selected 791 MW of the New England Wind 1 project. 


NEW 2 (retained by Commonwealth Wind): Phase 2 is planned to have an installed capacity of up to 1,080 MW, according to the documents at BOEM. On January 19, 2025, the EPA issued the final Clean Air Act Title V operating permit for Commonwealth Wind, LLC’s New England Wind 2 Offshore Wind Energy Development Project. Despite receiving federal approvals, the project is currently contingent upon New England Wind 1 moving forward. 


 

Delayed or Paused Projects: Seven projects representing 11.5 GW of renewable electricity.


Vineyard Northeast: Avangrid & Copenhagen Infrastructure Partners (CIP) proposes to construct and operate Vineyard Northeast which covers approximately 132,370 acres and is located approximately 31 miles from Nantucket, Massachusetts and 39 miles from Martha’s Vineyard, Massachusetts. According to the Construction & Operations Plan (COP), Vineyard Northeast will include 160 total wind turbine generators (WTG) and is projected to generate around 2.6 GW of electricity, with the potential to power over 900,000 homes. 


Status: Permits have been submitted to federal authorities in mid-2024 but have not yet been approved and are unlikely to be under the Trump administration. It is assumed that this project is delayed due to political uncertainty. 


Attentive Energy: In 2022, Attentive Energy participated in a bid for a lease area in the New York Bight, covering 132 square miles off the coast of New York and New Jersey. Attentive Energy, a joint venture between TotalEnergiesCorio Generation, and Rise Light & Power, decided to split the site into two projects: AE1 & AE2. In October 2023, the Attentive Energy One (1,400 MW) project was selected in New York’s third competitive offshore wind solicitation, which was later canceled due to ”technical and commercial complexities between provisional awardees and their partners”. The company decided not to rebid in New York’s latest offshore wind solicitation. 


Attentive Energy 2 (AE2): A Project off the coast of New Jersey with a capacity of 1,342 MW. In January 2024, it was selected by the New Jersey Board of Public Utilities (NJBPU). AE2 was set to move forward, with plans to continue development despite putting a pause on AE1 in New York due to potential political hurdles. The project was expected to be operational by 2031 but has been delayed for up to 4 years due to political uncertainties. 


Status: As of January 23 2025: Attentive Energy 2 have filed a 'Motion for Limited Stay' to the New Jersey Board of Public Utilities (NJBPU) asking for a year-long delay to pay required securities for the projects Commercial Operation Date (COD) commitment. The first payment, a deposit of USD 33.5 million, was due on 24 January 2025 alongside a USD 3.7 million payment with the state's Research and Monitoring Initiative (RMI). The reasons for this motion are cited as 'delays or uncertainty associated with common infrastructure'. 


Atlantic Shores South (Project 1 & 2): Atlantic Shores Offshore Wind, LLC (ASOW) is a 50:50 partnership between Shell and EDF Renewables North America and its Lease Area is located approximately 10-20 miles off the coast of New Jersey between Atlantic City and Barnegat Light. ASOW owns three lease areas (Atlantic Shores North, Atlantic Shores South, & The New York Bite) totaling more than 400 square miles under active development. Atlantic Shores South Project 1 and 2 have a total capacity of up to 2,800 MW of clean, renewable energy that BOEM estimates could power close to one million homes each year. The projects are approximately 8.7 miles offshore New Jersey at its closest point. The approved COP includes up to 197 total positions for wind turbine generators, offshore substations, and a meteorological tower, with subsea transmission cables making landfall in Atlantic City and Sea Girt, New Jersey. Projects in the other two other lease areas are still in the planning phase and have not yet been approved. 


Status: In June of 2021, the New Jersey Board of Public Utilities awarded Atlantic Shores Offshore Wind a contract to develop 1,510 MW in offshore wind energy, enough to power up to over 700,000 homes. On October 1st 2024, Atlantic Shores announced that it had received Construction and Operations Plan (COP) approvals from the Bureau of Ocean Energy Management (BOEM) for Projects 1 and 2. Following the changing political landscape and executive orders barring new offshore wind leasing, Shell pulled out of the project and EDF booked a $980 million impairment. EDF says it still hopes to build the project but is silent on when. As of May 14th, 2025, a federal appeals board ordered that a crucial air quality permit the U.S. Environmental Protection Agency issued in October under the Biden Administration to be revoked, sending it back to the agency for further consideration. 


South Coast Wind 1 & 2: OW Ocean Winds plans to build South Coast Wind 1 (formerly Mayflower Wind) which will deliver approximately 1,200 MW via an electric grid connection at Brayton Point/Somerset, Massachusetts in the late 2020s. The project area covers approximately 127,388 acres and is about 26 nautical miles (nm) south of Martha’s Vineyard and 20 nm south of Nantucket, Massachusetts. The approved COP includes the construction of up to 141 wind turbine generators and up to five offshore substation platforms located at a maximum of 143 positions, and up to eight offshore export cables located in up to two corridors, potentially making landfall in Brayton Point or Falmouth, Massachusetts. SouthCoast Wind is also looking at Brayton Point for interconnection of the second 1,200 MW of electricity generated in the lease area from South Coast Wind 2. Falmouth, MA continues to remain an option for this second phase while grid capacity and timing of necessary upgrades are determined. 


Status: On January 17, 2025, BOEM announced the approval of the SouthCoast Wind Project Construction and Operations Plan (COP). The lease area has the potential to generate up to 2,400 MW of renewable energy for New England and power over 840,000 homes. EDPR and Engie recently booked an impairment of $139 million each and said the construction could be pushed back by up to 4 years from 2025 to 2029. They expect a delay due to the current administration and took a write-down on the asset to reflect the possibility of a four-year delay. 


Leading Light WindThe Leading Light Wind project, a 2.4 GW offshore wind farm proposed by Invenergy and energyRe around 40 miles off the coast of New Jersey, is facing significant delays due to ongoing volatility in the wind turbine equipment market. Initially selected by the New Jersey Board of Public Utilities (NJBPU) in January 2024, the project encountered setbacks when its planned turbine supplier, GE Vernova, ceased production of the intended 18 MW turbines. Subsequent negotiations with Siemens Gamesa Renewable Energy resulted in substantial cost increases, and Vestas was deemed unsuitable, leaving Invenergy without a viable supplier. 


Status: Invenergy has requested multiple delays from the NJBPU, extending the project's contract pause to May 20, 2025, to navigate these challenges. The project was originally scheduled to begin construction in 2028 and operations in 2032 but this timeline is subject to change. Despite facing challenges, Invenergy remains committed to the project, emphasizing its potential environmental and economic benefits for New Jersey. 


 

Temporarily Cancelled Projects: Ten projects representing 9.6 GW of renewable electricity. While not all of these projects have been officially terminated, many require restructuring due to changes in market conditions, likely resulting in significant delays. 


Ocean Wind 1 and 2: Ocean Wind 1 (1,100 MW) and Ocean Wind 2 (1,148 MW) were planned to be built off the coast of New Jersey totaling 2.2 GW of potential generation. In late 2023, Ørsted decided to cease the development of Ocean Wind 1 and 2. The projects experienced significant impacts from macroeconomic factors, including high inflation, rising interest rates and supply chain constraints, particularly a vessel delay on Ocean Wind 1 that considerably impacted project timing. The company intends to retain the seabed lease area and consider the best options as part of the ongoing portfolio review. Ørsted agreed to pay New Jersey $125 million to settle claims over the company's cancellation of the two offshore wind farm projects. 


Skipjack Wind 1 & 2The Skipjack Wind project, a 966 MW offshore wind project, was planned to be Maryland's first offshore wind project, located off the coast of the Delmarva Peninsula. In January 2024, Ørsted terminated its offtake agreement with the State of Maryland for the project, citing challenging market conditions (inflation, high-interest rates, and supply chain constraints). While Ørsted terminated the offtake agreement, they stated that they will continue advancing development and permitting for the project, including submitting an updated Construction and Operations plan to the Bureau of Ocean Energy Management (BOEM). They also plan to reposition the project for future offtake opportunities. This decision came shortly after Ørsted cancelled its Ocean Wind projects in New Jersey. 


Vineyard 2: A proposed 1,200 MW offshore wind project that could have powered 650,000 New England homes. While Massachusetts had agreed to buy 800 MW, the project's full viability depended on Connecticut's participation. The project is no longer moving forward in its original form because Connecticut declined to purchase the remaining 400 MW needed to complete the project, opting for solar and storage projects instead. Consequently, Vineyard Offshore withdrew from contract negotiations, as they couldn't secure the full 1,200 MW. 


Attentive Energy 1, Community Offshore Wind, and Excelsior Wind: 

In April 2024, the New York State Energy Research and Development Authority (NYSERDA) cancelled three offshore wind projects, that had received provisional awards in October 2023, due to "technical and commercial complexities" and a change in turbine design by GE Vernova. A key factor in the cancellations was GE's decision to halt development of an 18-MW variant of its Haliade-X turbine, which the projects were planned to use. They decided to shift their focus to smaller turbines (15.5/16.5 MW) which led to technical and commercial complexities, making the projects no longer viable. This shift to smaller turbines meant that developers would need to install more turbines to achieve the promised electricity output, which would increase project costs dramatically. These cancelled projects represent 4 GW of provisionally awarded capacity. 


Attentive Energy 1 (AE1): A 1,400 MW project set to deliver clean electricity to New York. AE1 was cancelled by NYSERDA in April 2024 due to changes in turbine technology from the preferred provider GE Vernova, which significantly impacted the cost and feasibility of the projects. NYSERDA launched New York's fifth competitive offshore wind solicitation (ORECRFP24-1) on July 17, 2024. Attentive Energy rebid the project but later withdrew. Attentive Energy cited the need to continue evaluating market conditions and future opportunities, while remaining committed to deploying offshore wind and contributing to regional goals. 


-AE’s statement from October 21, 2024: “Attentive Energy has decided to withdraw its bid from New York State’s fifth solicitation for offshore wind projects. Attentive Energy commends the State’s steadfast support of offshore wind and will continue to evaluate market conditions and future opportunities as they arise. As Attentive Energy continues to advance opportunities from our lease area, we remain committed to deploying offshore wind and contributing toward our region’s shared economic and environmental goals.” 


Community Offshore WindRWE and National Grid have partnered to jointly develop offshore wind projects in the Northeast U.S. As of October 18, 2024, Community Offshore Wind submitted their full proposal to provide clean offshore wind energy for the State of New York. The proposed project could deliver up to 2.8 GW of renewable energy, built in two phases in the developer’s federal offshore wind lease area in the New York Bight. 1,314 MW was planned to be developed in the first phase but was cancelled by NYSERDA. 


Excelsior Wind: Vineyard Offshore (owned by Copenhagen Infrastructure Partners) plans to build a 1,350 MW project in the New York Bite, approximately 24 miles off the coast of Long Island. The wind farm would deliver enough electricity to power more than 700,000 New York homes. BOEM began an environmental review for Vineyard Mid-Atlantic where the project is located in January 2025. However, President Trump's memorandum pausing offshore wind activities led to the cancellation of scheduled public meetings, effectively halting the review process. 


Empire Wind 2: Equinor and bp terminated the Empire Wind 2 project, a 1,260 MW offshore wind farm, citing increased costs, supply chain disruptions, and changing commercial conditions. The companies stated that inflation, interest rates, and supply chain disruptions made the project's existing Offshore Wind Renewable Energy Certificate (OREC) agreement no longer viable. The cancellation also included the termination of contracts for an offshore substation platform and scour rock installation. The project, previously a joint venture between Equinor and BP, has been reset, and the OREC agreement has been terminated. Equinor now holds full ownership of the Empire Wind projects (including Empire Wind 1 and 2), while BP has taken full ownership of Beacon Wind, which is still in the development process. 


Ice Breaker Wind (Great Lakes Pilot Project): The 20 MW project, spearheaded by the Lake Erie Energy Development Corporation (LEEDCo), aimed to install six wind turbines about eight miles off the Cleveland shoreline to test the feasibility of offshore wind power in the Great Lakes. Intended to be the first freshwater offshore wind farm in North America on Lake Erie, was put on hold indefinitely in December 2023 due to rising costs, challenges, and delays, despite having obtained all necessary permits. LEEDCo remains open to the possibility of partnering with another developer to take over the project, and board members remain optimistic that the project will come to fruition in Cleveland. 


 

Resources: Stay up to date on the status of ongoing offshore wind projects in the U.S. 


Offshore Wind Power Hub: tracks offshore wind policies, projects, and lease areas in the United States, and provides a platform for advocates and policymakers to collaborate and share resources. Check out this interactive map to see all of the ongoing projects in the U.S. 


Northeast Ocean Data Portal: provides free, user-friendly access to expert-reviewed interactive maps and data on the ocean ecosystem, economy, and culture of the northeastern United States.


4C Offshore (TGS) Offshore Wind Database: 4C Offshore marine intelligence software provides exclusive access to a range of specialized services including the Offshore Substation Database, offline databases, reports, newsletters, online tools and more. You will need Full access to use the 4C Offshore interactive system, access reports, updates, news, and downloads. 


BOEM Offshore Renewable Activities: Search by state or project for information on U.S. offshore wind projects or use the interactive map. 